If the Scheduled Trigger and Task Event Trigger run in the same way, how they work? "OR" or "AND"?
For example, I have 2 triggers in 1 task:
T1. Daily trigger run every 10:00 AM
T2. Task event trigger run if another task successfully
The case is, time show at 10:01 AM but task event trigger (T2) not yet finished.
What would happen?
The task will run, or wait until T2 completely finished?
Based on my understanding the events are OR events. If either of the two events complete, the application will refresh. So, in the example that you put out, the application will refresh at 10:00 AM regardless of if the Task event trigger have successfully completed or not