what is the different =Date or Date in dimension ?

Hi All

I notice that for QS , when i bring in a field to dimension.

I can write =Date or Date

May i know does it make any different ?

Paul

1 Solution

Accepted Solutions
ahaahaaha
Partner - Master
Partner - Master

Hi Paul,

In idea, the "=" sign is a sign of the calculated expression. If the dimension is calculated, then "=" is mandatory, otherwise Qlik Sence recognizes in any case with a "=" or not.

Regards,

Andrey

View solution in original post

7 Replies
Anil_Babu_Samineni

Check the difference and In dimension usually it indicates Calc. Dim and plane dimension i would say

Example sum.jpg

Best Anil, When applicable please mark the correct/appropriate replies as "solution" (you can mark up to 3 "solutions". Please LIKE threads if the provided solution is helpful
sunny_talwar

I don't think there is any difference? Do you see any difference?

paulyeo11
Master
Master
Author

Hi Talwar

So far i see not different. So i think better don't put = infornt , as Label will display =Date.

Paul

ahaahaaha
Partner - Master
Partner - Master

Hi Paul,

In idea, the "=" sign is a sign of the calculated expression. If the dimension is calculated, then "=" is mandatory, otherwise Qlik Sence recognizes in any case with a "=" or not.

Regards,

Andrey

sunny_talwar

I agree

paulyeo11
Master
Master
Author

Hi Anil

For expression if insert directly into it , it should not have be different. but it automatic display total amount , if with out need click on total function = sum ( i am not yet try using variable )

Paul

praveen_prithiviraj
Contributor III
Contributor III

Yes, This is correct Andrey