Hi guys,
I have 2 questions - one is probably easy, and the second a bit tougher.
Q1: I have a calendar where I am importing a distinct list Public Holidays.
e.g.
PublicHolidays:
Load Date From [$(vL.QVDSourcePath)Master_MS_Calendar.qvd] (qvd)
WHERE AustPublicHoliday=1; --> This produces a list of 87 public holidays (that are valid until the year 2020).
-->It's in the QVD so I can use the same list of public holidays in multiple applications (and just update the Master Calendar in future).
However, I then want to use this list in the NetWorkDays function, as an array , so in place of the below:
networkdays (start_date, end_date [, holiday])
I want to have:
networkdays (start_date, end_date, vPublicHolidays)
So Question 1 is: How can I pass the holiday values I've loaded into my public holidays table (if it is at all necessary to load them into a table...), and store them into an array vPublicHolidays?
Ok. Q2:
Qlik Sense Has a NetWorkDays function. I have to build a valid Cycle Time calculation between 2 days for transactions that are processed for an administration department.
Their business hours are from 8am-7pm.
Therefore, I need a 'Business Days' (NetWorkHours) calculation that:
a) only accumulates hours between the 11 hours of 8am to 7pm
b) skips weekends
c) skips public holidays
To further explain this -
1..total hours in a day is 11; and time is only accumulated between 8-7pm Mon-Fri
2. if overtime was done on a Saturday, and work was completed. it would count as being completed on the Friday (as an example).
Any help would be greatly appreciated.
Thanks
Peter
Hi there,
Thanks for the response.
This is helpful however as per the question am looking for calculation that correctly accounts for Business Hours
Thanks
Peter
Just wondering if anyone has any ideas?
Thanks
Pete
For anyone interested, the answer was here Business Working Hours Calculation