Reference line for Selected months

Hi all

I need to show reference line in chart.following expression is working  if i select any one month or 2 or 3 consecutive months. if i select random months answer was not correct. can anyone suggest?

    (NetWorkDays(Date(min(Date),'DD-MMM-YYYY'),Date(max(Date),'DD-MMM-YYYY'),$(v_Holiday)) * 8.5))

for examlpe

     apr-170 hrs

     may-187 hrs

     june-178.5 hrs

    July-178.5 hrs

    aug-178.5 hrs

    Sep-76.5 hrs

From the above if i choose apr&may combination- 357

                                        may&june combination-365.5

                                         apr& june combination- 535.5(apr+may+june) (but i need to get 348.5 for Apr & june)

5 Replies
mdmukramali
Specialist III
Specialist III

Hi,

Can you share sample data Application.

Thanks,

Mukram

shraddha_g
Partner - Master III
Partner - Master III

Share sample app

KumaRan
Contributor III
Contributor III
Author

PFA

Neymar_Jr
Creator II
Creator II

Hi,

Please find attached the updated app.!

Hope it meets your requirement.

Cheers!

KumaRan
Contributor III
Contributor III
Author

Hi Rajesh

  Thank you for your time. its working fine. but my question is ,in future if months are added, do i need to modify expression isn't?

    If answer for the above question is YES i need to automate it without adding any expression.Kindly can you suggest?