How to schedule trigger task in 9.0

Hi,

I want to schedule a task2 which is run after completion of task1.

when i am looking to qvs ref manual 118 it is showing to schedule a trigger task ( following options are there start on , run only between , run only on , max number of execution & Expire ) but when I am opening my QEMC there I am getting option only start on other options are not there.

Earlier I was using 9.0 SR2 now updated to SR3, but I am not finding that option either in SR2 or SR3.

can any body tell how that option comes.

thanks

1 Reply
vgutkovsky
Master II
Master II

In the drop-down, select Start The Task "On Event From Another Task."

Regards,