hello everyone

I have put a calendar on my app on the local version it show the month and year of date

version locale.PNG

and on the accesspoint point version it shows "today" for any chosen date :s

version web.PNG

thank you for your help

5 Replies
maksim_senin
Partner - Creator III
Partner - Creator III

Hi everybody,

Also I found that week numbers in the AJAX calendar do not match with the ones returned by WeekName() function.

calendar_ajax.PNG

Does anyone know whether it's possible to change this???

Thanks.

Best regards,

Maxim

P.S. As far as I understand the calendar is a third-party component, the text below is shown in it's help (? sign). As I can see at the link, the calendar at the page shows correct week numbers, may be QlikTech just needs to integrate a newer version?

DHTML Date/Time Selector

(c) dynarch.com 2002-2005 / Author: Mihai Bazon

For latest version visit: http://www.dynarch.com/projects/calendar/

maksim_senin
Partner - Creator III
Partner - Creator III

Hmmm... a joke from the calendar developer:

- old version which has the bug with week numbers, the version all we use - http://www.dynarch.com/projects/calendar/old/

- new version which seems does not have the bug - http://www.dynarch.com/projects/calendar/

HELP!

maksim_senin
Partner - Creator III
Partner - Creator III

I've tried playing with .js files located in QV server folders (changing "firstday" parameter as it's recommended at http://www.dynarch.com/projects/calendar/old/), but failed.

Can someone from QlikTech comment on this issue please.

Thanks.

Not applicable
Author

HI, I have the same problem on 11.20 sr3, Did you solved this problem? Maybe updating Qlik version also update the dhtml calendar version?

Thanks.

senarath
Creator III
Creator III

Hi,

Issue is the different versions in the server and the desktop. If I could remember correct, SR5 onward only you get the user friendly version of calender which is a major fix.

thanx

Senarath