Gap Analysis with a Stacked Bar Chart

Dear Community,

I have a problem in creating a Stacked Bar Chart.

The basics are clear to me, that means I know how to create a Stacked Bar Chart.

Unfortunately I'm not able to meet my requirement in total.

Short description of my Problem:

I have to build up a Chart that compares a actual value with a planned value.

For example, I need to visit 6 Clients per day and my actual is 4.

Now I want to show a chart that shows the actual part of the bar in green.

The part of the missing 2 visits must be displayed in Yellow.

So everybody can see the gap.

Furthermore there is another scenario that could happen.

A person might be able to visit 8/6 clients a day.

Now the chart should look as the following. The planned area (6) need to be displayed in green.

The part of the more visits need to be displayed in red.

I hope you understand my problem.

I'am looking forward to your comments.

1 Solution

Accepted Solutions
Gysbert_Wassenaar

See attached qvw. Is that what you're looking for?


talk is cheap, supply exceeds demand

View solution in original post

5 Replies
Gysbert_Wassenaar

See attached qvw. Is that what you're looking for?


talk is cheap, supply exceeds demand
Not applicable
Author

Gysbert that is exactly what I'm looking for!

Thank you very very much for the quick answer!

Perfect!

Not applicable
Author

Hi Gysbert, do you have any ideas how I can design the qvw that it looks like this example?

Calls.jpg

hschultz
Partner - Creator
Partner - Creator

Hi there.

Is this what you are looking for?

Not applicable
Author

Thank you very much. That is what I'm looking for.