Computing for Days Delayed

Hello,

I would like to compute for the days delayed in my file. The problem is, the date that I have to compute is only located in 1 field.

Please see attached file!

Thanks,

Donna

********************[UPDATE]****************************

Since we can now compute the days delayed (answer provided by Flipside).. I have a situation which I have to input in an input box,

ex: Days Delayed [input box]: 3, if I input a number, it will only display the days delayed which is equal to 3.

is this possible?

Thanks a bunch!

-Dona

11 Replies
Not applicable
Author

thanks flipside! it works! now my only problem is to show also the date it was shipped. are there possible ways to show it on the dimension without getting the 'error in calculation'?

thanks!!

Not applicable
Author

up~