I need to create a seamless Time Dimension, based on Start Time

2014-03-03_1448.png

Hi All,

The above chart is a pivot table, The background color changes based on the task being performed

The times at the top are the start times of the task.

My question is how can I get a more seamless chart, basically I would like the chart to always have the 24 hours in a day but with the tasks colored where it fits in with the time of the day.

I hope that makes sense.

Regards

Alan

13 Replies
rustyfishbones
Master II
Master II
Author

Thanks Aunez,

I will try this and revert

Thanks again

Regards

Alan

Not applicable

Well,

try Henric's solution first. It is certainly more robust (I did not see he had answered). But you got the way to do it.

Fabrice

IAMDV
Luminary Alumni
Luminary Alumni

Hi Alan,

I'm recommending this article by just reading the subject line. And also read Henric's post:

http://community.qlik.com/blogs/qlikviewdesignblog/2013/02/12/reference-dates

and one more very useful post

http://iqlik.wordpress.com/2011/05/22/a-new-choice-of-armor-the-flag-matrix/

Thanks,

DV

rustyfishbones
Master II
Master II
Author

Thanks Deepak