Run reload tasks in paralel

Hi

I have several reload tasks as follows:

Extraction task

Transformation Task 11

Transformation Task 12

Transformation Task 13

Transformation Task 2

I would like to achieve the following:

1. Run "Extraction Task".

2. Run "Transformation Task 11", "Transformation Task 12", "Transformation Task 13" in paralel after "Extraction Task" is completed.

3. Run "Transformation Task 2" after all "Transformation Task 11", "Transformation Task 12", "Transformation Task 13" are completed.

Is it possible to do with QMC? If not what flow package would you suggest?

Thanks

Darius

14 Replies
Not applicable

I think you may define triggers and this way manage task order.

regards

Darek

d_pranskus
Partner - Creator III
Partner - Creator III
Author

Hi

What triggers you have in mind? Is it in the QlikView itself? Or is it in QMC?

Thanks

Darius

d_pranskus
Partner - Creator III
Partner - Creator III
Author

Hi

I understand, that it is possible to start several tasks simultaneously as a result of trigger from another task. But how to force sub-sequential task to wait until all previous tasks are completed.

Thanks

Darius

ashfaq_haseeb
Champion III
Champion III

Hi,,

yes possible,

See the attached image below.

Regards

ASHFAQ

d_pranskus
Partner - Creator III
Partner - Creator III
Author

Thanks Ashfaq

Does this require special license? I am unable to find the screen you provided. The only one I see is this:

Screen Shot 2014-05-14 at 14.13.54.png

Thanks

Darius

ashfaq_haseeb
Champion III
Champion III

Hi

Select on event from another task.--> Successful --> Select multiple task from drop down.

Regards

ASHFAQ

Clever_Anjos
Employee
Employee

1) Into QMC configure "Extraction Task" daily (or whatever)

2) Configure Transformation tasks as " On Event from Another Task "

Capturar.PNG.png

d_pranskus
Partner - Creator III
Partner - Creator III
Author

Hi

Unfortunatelly I can select only one task in the dropdown.

Cheers

Darius

d_pranskus
Partner - Creator III
Partner - Creator III
Author

Hi

This is not what I am asking. I want the task be dependent on completion of multiple tasks.

Thanks

Darius