How to Calculate Median number of days to close compliance/risk?

Hi All, 

 

Have a nice day.

I have two date fields CteateDate, UpdateDate here i need to calculate MEDIAN NUMBER DAYS to close a risk by using these two date fields . so how to calculate median in qliksense.

 

Kindly help in this to calculate median number of daty.. to take to close the risk.

 

 

Thanks every one...!

4 Replies
Anil_Babu_Samineni

Can you explain with some example?

Before develop something, think If placed (The Right information | To the right people | At the Right time | In the Right place | With the Right context)
narayanaqlik
Creator
Creator
Author

Thanks for quick reponse  MVP

here i need to calculate median number days to close a risk

 here i have two dates fields one is CreateDate field and another one is UpdateDate 

some risk will take 7 days some risk will take 10, 12, 15... son like (i.e CtreateDate-UpdateDate)

but here i need to calculate median number of days to take to close the risk How?

Anil_Babu_Samineni

Perhaps this

Median(Interval(CtreateDate-UpdateDate, 'DD'))

Before develop something, think If placed (The Right information | To the right people | At the Right time | In the Right place | With the Right context)
narayanaqlik
Creator
Creator
Author

Hi Anil Babu,

Thanks for giving good response , yes it is working fine 

if we want apply conditions how can we apply for same median number calculations 

 

 if i want to do  calculation only for closed risks , i need to calculation median number days to close the risks.

Could you please give the suitable logic Very Thanks....!