Hi ,
I need to sum quantity based on input dates with below expression.
If the user enters 0 to 10 in the days input then I need to sum up the quantities between days 0 to 9
And if the user gives input has 18 to 25 , I need to some up quantities from 18 to 25 days
similarly , it needs to sum the quantity based on user input.
So the beginning date in the shift date always has the current date.
For example, if today is 2022-09-05. The Shift Date has date starting from 2022-09-05. And the end date is 70 days from current date.
I'm not sure whether I've defined the variable in a correct way.
Please, some one help let me know where I'm going wrong
=sum({<$(='[Shift Date]')={">=$(vStart)<=$(vEnd)"}>} Quantity)
output : 0
The shift date is in the format, 2022-09-02.
I'm receiving 0 no matter the input I give on vStart and vEnd.
Where the variables are defined as vStart= 0 and vEnd = 0.
Try this:
=sum({<[Shift Date]={">='$(vStart)'<='$(vEnd)'"}>} Quantity)
I am assuming that both Shift Date, vStart and vEnd are formated as your application default date format.
use below
Sum({<Quantity={">=$(vQuantityStart)<=$(vQuantityEnd)"},Date={">=$(vMinDate)<=$(vMaxDate)"}>}Quantity)
using attached Excel and .qvf
you Can ENter min and Max Quanity , also Min Date and Result will Change according to entry.
Hope this helps