Hi experts,
Hope you are doing good.
I have a requirement to execute the Qliksense script only when the data is available in the update table. Below is what i have done so far.
Table 1: Direct load from DB and pulls the maximum date
Table 2: Load from QVD and pulls the maximum data
LET vcurrentdate = peek('vcurrentdate',0,'vcurrentdate');
LET vpreviousdate = peek('vpreviousdate',0,'vpreviousdate');
After this i am assigning a new variable value to check if the current date is greater than the previous date i.e.,
If $(vcurrentdate) > $(vpreviousdate) then
LET vupdate = 'True'
else
Let vupdate = 'False'
END If;
// Starting to check the db update
Do while vupdate = 'False'
If vupdate = 'True' Then
Exit Script
Else
Sleep (10000)
Let vupdate = '';
// Again loading the date from Table 1 & 2 here
Table1:
Load Max(date) as currentdate
From sql.updatetable;
Table 2:
Load Max(date) as previousdate
From Date.qvd;
// Again checking and assigning the dates
LET vcurrentdate = peek('vcurrentdate',0,'vcurrentdate');
LET vpreviousdate = peek('vpreviousdate',0,'vpreviousdate');
If $(vcurrentdate) > $(vpreviousdate) then
LET vupdate = 'True'
else
Let vupdate = 'False'
END If;
END IF;
Exit Do when vupdate = 'True'
Loop;
//
Problem i am facing now is it is going into infinite loop even when the vcurrent date is updated while the app reload is in process. Once i stop and re-run the application then it is working since it is satisfying the condition. I am not sure as what is the problem here.
Any help on the same is highly appreciated. Thanks in advance.
*PS - I am not in a position to post / share any data as it is from a highly restricted source. Please excuse and hope you understand.
I refined your code a little bit, try this :
//Initial Load and Variable Assignment:
//Load the maximum dates from the database and QVD.
//Assign these dates to variables.
Table1:
Load Max(date) as currentdate
From sql.updatetable;
Table2:
Load Max(date) as previousdate
From Date.qvd;
LET vcurrentdate = peek('currentdate', 0, 'Table1');
LET vpreviousdate = peek('previousdate', 0, 'Table2');
//Check for Data Update:
//Compare the dates and set the vupdate variable accordingly.
IF $(vcurrentdate) > $(vpreviousdate) THEN
LET vupdate = 'True';
ELSE
LET vupdate = 'False';
END IF;
//Loop to Check for Updates:
//Use a loop to periodically check for updates, but ensure it exits correctly.
DO WHILE $(vupdate) = 'False'
Sleep 10000; // Wait for 10 seconds before checking again
// Reload the dates
Table1:
Load Max(date) as currentdate
From sql.updatetable;
Table2:
Load Max(date) as previousdate
From Date.qvd;
// Reassign the dates
LET vcurrentdate = peek('currentdate', 0, 'Table1');
LET vpreviousdate = peek('previousdate', 0, 'Table2');
// Check for update
IF $(vcurrentdate) > $(vpreviousdate) THEN
LET vupdate = 'True';
ELSE
LET vupdate = 'False';
END IF;
// Exit loop if update is found
IF $(vupdate) = 'True' THEN
EXIT DO;
END IF;
LOOP;
//Exit Script:
//Ensure the script exits correctly once the update is detected.
IF $(vupdate) = 'True' THEN
EXIT SCRIPT;
END IF;
Hi Sayed,
Thank you for taking time in replying.
Unfortunately the script is still looping even if the data is updated.
I tried to set the variables to NULL before starting the DO WHILE in case if that was the problem but still the script is running in infinite loop.
/Check for Data Update:
//Compare the dates and set the vupdate variable accordingly.
IF $(vcurrentdate) > $(vpreviousdate) THEN
LET vupdate = 'True';
ELSE
LET vupdate = 'False';
END IF;
// Updated below code
IF vupdate = 'False' THEN
LET vcurrentdate = NULL();
LET vpreviousdate = NULL();
END IF;
//Loop to Check for Updates:
//Use a loop to periodically check for updates, but ensure it exits correctly.
DO WHILE $(vupdate) = 'False'
Sleep 10000; // Wait for 10 seconds before checking again
You could avoid it by changing the loop-type, maybe: for i = 1 to n and also using the iterator to adjust the sleep like: sleep 10000 * $(i);
Hi all, thank you for your inputs.
I found the issue and was able to achieve the loop exit once the update is available in DB.
I simply changed the table reference before and after the loop has started.
Table 1: Direct load from DB and pulls the maximum date
Table 2: Load from QVD and pulls the maximum data
LET vcurrentdate = peek('vcurrentdate',0,'vcurrentdate');
LET vpreviousdate = peek('vpreviousdate',0,'vpreviousdate');
After this i am assigning a new variable value to check if the current date is greater than the previous date i.e.,
If $(vcurrentdate) > $(vpreviousdate) then
LET vupdate = 'True'
else
Let vupdate = 'False'
END If;
// Starting to check the db update
Do while vupdate = 'False'
If vupdate = 'True' Then
Exit Script
Else
Sleep (10000)
Let vupdate = '';
// Again loading the date from Table 1 & 2 here, changed the table name to 3 & 4
Table3:
Load Max(date) as currentdate
From sql.updatetable;
Table 4:
Load Max(date) as previousdate
From Date.qvd;
// Again checking and assigning the dates
LET vcurrentdate = peek('vcurrentdate',0,'vcurrentdate');
LET vpreviousdate = peek('vpreviousdate',0,'vpreviousdate');
If $(vcurrentdate) > $(vpreviousdate) then
LET vupdate = 'True'
else
Let vupdate = 'False'
END If;
END IF;
Exit Do when vupdate = 'True'
Loop;