psenthilbtech
New Contributor II

Count Days

Hi Team,

I have 2 Measures,

1. Sum(Actual)

2. Sum(Plan)

I have the records from 1st Jan 2018 till Date

The requirement is , i have to count the no of distinct days where my  sum(Actual) < sum(Plan).

Can anyone help me on this

Tags (1)
2 Replies
andrey_krylov
Valued Contributor

Re: Count Days

Hi, If there is a date field in the model try this

Sum(if(Aggr(sum(Actual) - sum(Plan), DateField) < 0, 1, 0))

maddysalunke
New Contributor

Re: Count Days

Hi Senthil,

If you want to calculate for all days , then you can use =Date2-Date1

And if you want to calculate working day, then use =Networkdays (StartDate, EndDate {, Holiday})

You can write the expression as ,

if (sum(Actual) < sum(Plan),Networkdays (StartDate, EndDate {, Holiday}))


or

if (sum(Actual) < sum(Plan),Date2-Date1)


The Networkdays () returns the number of working days (Monday-Friday) between and including StartDate and EndDate taking into account any optionally listed holidays. All parameters should be valid dates or timestamps.


Thanks,

Madhura