Qlik Community

New to Qlik Sense

Discussion board where members can get started with Qlik Sense.

Announcements
Qlik® Product Spotlight: Discover what’s possible. Get more from our products.
See for yourself. Register today.
zebhashmi
Valued Contributor

Hard Date vs Calculated

Sum({<Date_End ={'5/21/2018'}>}Salary) this is working

and this is not working

Sum({<Date_End ={"=Date(floor(ReloadTime()),'MM/DD/YYYY')"}>}Salary)

any idea?

1 Solution

Accepted Solutions

Re: Hard Date vs Calculated

Try this

Sum({<Date_End = {"$(=Date(Floor(ReloadTime()), 'M/D/YYYY'))"}>}Salary)

2 Replies

Re: Hard Date vs Calculated

Try this

Sum({<Date_End = {"$(=Date(Floor(ReloadTime()), 'M/D/YYYY'))"}>}Salary)

zebhashmi
Valued Contributor

Re: Hard Date vs Calculated

I believe I tried that

But it worked with yours

Thank you very much!