Hello.

I used the following expression under Sort section: Match(cpt4_code_id, '99201', '99202' , '99203', '99204', '99205')

Works great:

150c8aaefb0d486192b43052ad8f25f0.jpg

However, when I select a filter for a specific provider name, the sort no longer works.

76bbdba35edc4816894cb3b79f5ad754.jpg

Measure 1:

Count({$<cpt4_code_id={'99201','99202','99203','99204','99205'}>}cpt4_code_id)/Count(total{$<cpt4_code_id={'99201','99202','99203','99204','99205'}>}quantity)

Measure 2:

Count({1<cpt4_code_id={'99201','99202','99203','99204','99205'}>}cpt4_code_id)/Count(total{1<cpt4_code_id={'99201','99202','99203','99204','99205'}>}quantity)

How come the order doesn't follow what is in the expression?

Match(cpt4_code_id, '99201', '99202' , '99203', '99204', '99205')


1 Solution

Accepted Solutions
sunny_talwar

Try this:

Match(Only({1} cpt4_code_id), '99201', '99202' , '99203', '99204', '99205')

View solution in original post

6 Replies
sunny_talwar

Try this:

Match(Only({1} cpt4_code_id), '99201', '99202' , '99203', '99204', '99205')

Not applicable
Author

That worked! How come I needed to apply Only?

Thanks Sunny!

sunny_talwar

Because based on the selection made the cpt4_code_id was converting to null for not selected items. In order to restrict selections we needed to add {1} and this can only be added within a aggregation function such as Only().

Not applicable
Author

Thank you!!!  I just tried that with a sort order I've been struggling with.  Awesome

irfanmd2010
Contributor
Contributor

Thank you , I also had same issue

emroenor
Contributor
Contributor

Hi, the {1} is not working for me. I used this Expression but the graph is not displaying in the right order.

Match(Only({1} [3M Next Milestone]),'Pre Imp: Quote Request', 'Pre Imp: TRR', 'Pre Imp: Site Survey','Pre Imp: HLD + BOM','Pre Imp: SOW/Proposal & PO', 'MS1: Project Kick-off', 'MS2: Eng Design + LLD/Workpack', 'MS3: Equipment Ordering', 'MS4: Equipment Delivery', 'MS5: Site Remediation', 'MS6: Implementation Preparation', 'MS7: Implementation', 'MS8: ORT/NOC Handover', 'MS9: Project Closeout') 

Can you help me on this? Thanks.