Hi guys,

Is there a way to trigger a task once a previous task has started? I know we can do it on successful / failed but I would like to kick one off when another has started.

Is that possible?

Thanks

 

Labels (3)
1 Solution

Accepted Solutions
TimvB
Creator II
Creator II

What triggers the initial app reload? You can have the same trigger for the app that needs a simultaneous reload. If the initial app is triggered manually, you could create a dummy (empty) app that triggers the two apps after reload. The dummy app will be the start of the chain.

View solution in original post

2 Replies
TimvB
Creator II
Creator II

What triggers the initial app reload? You can have the same trigger for the app that needs a simultaneous reload. If the initial app is triggered manually, you could create a dummy (empty) app that triggers the two apps after reload. The dummy app will be the start of the chain.

jamelmessaoud
Creator II
Creator II
Author

I never even thought of a dummy app to kick them both off! Fantastic idea.