hi,
I am making a bar chat which is showing RunTime(y-axis) V/S Jobs(x-axis). But there are many Jobs which are running multiple times in a day. There may be possibility that on the same date and time , many jobs are running.
I used the below expression for Average value of RunTime taken by each Job in current week which is giving right value:-
=sum(aggr(sum(RunTime),Week, Jobs))/ Sum(aggr(Count(Job_Count), Week, Jobs))
But I am getting problem with the expression of Average value of RunTime taken by each Job in previous week. I am using below expression:
=Sum(aggr(sum({$<Week = {" $(=Week(Start_Date - 7)) "}>}RunTime),Week, Jobs))/ Sum(aggr(Count({$<Week = {" $(=Week(Start_Date - 7)) "}>}Job_Count), Week, Jobs)
Can somebody help me to know what is wrong with this expression.
You need to remove Date selection by using aggr ({<Start_Date=, Week=>}
hi Santosh,
I am not getting you. Can you please explain me more.
=Sum(aggr({<Week=>}sum({$<Week = {" $(=Week(Start_Date - 7)) "}>}RunTime),Week, Jobs))/ Sum(aggr({<Week=>}Count({$<Week = {" $(=Week(Start_Date - 7)) "}>}Job_Count), Week, Jobs)
It is not working. Some syntax error is coming. Can you suggest me something else.
I try the below expression
=Sum({<Week=>}aggr(sum({$<Week = {" $(=Week(Start_Date - 7)) "}>}RunTime),Week, Jobs)) / Sum({<Week=>}aggr(Count({$<Week = {" $(=Week(Start_Date - 7)) "}>}Job_Count), Week, Jobs)
but I am getting null value.
Hi Meenakshi,
I think you forgot a ')' parenthesis at the end of the expression.
Regards,
Giacomo
I used the below expression after using ')' parenthesis at the end of the expression. But I am getting null value.
=Sum({<Week=>}aggr(sum({$<Week = {" $(=Week(Start_Date - 7)) "}>}RunTime),Week, Jobs)) / Sum({<Week=>}aggr(Count({$<Week = {" $(=Week(Start_Date - 7)) "}>}Job_Count), Week, Jobs))
use sum in place of count .beacuse job count is already a count.try below
Sum({<Week=>}aggr(sum({$<Week = {" $(=Week(Start_Date - 7)) "}>}RunTime),Week, Jobs)) / Sum({<Week=>}aggr(sum({$<Week = {" $(=Week(Start_Date - 7)) "}>}Job_Count), Week, Jobs)