Unlock a world of possibilities! Login now and discover the exclusive benefits awaiting you.
Hello
I have attached a QVW which shows a gauge graph
In the gauge graph I have 3 segments on the presentation tab
I can only get 2 segments to show at the moment.
Could someone help me show the 3rd and in addition I would like the gauge graph to show Green, then grey and finally red, and am not sure how to achieve this
Thanks
Helen
You must change the Lower Limit of your last segment (the one you call Segment 2) to the sum of the both criterias:
=Count({<CRITERIA={'1) Dated - in time', '2) No date'}>} Identifier) / Count(Identifier)
The way you did it before, the last segment limit was smaller than the second one.
Juan Gerardo
You must change the Lower Limit of your last segment (the one you call Segment 2) to the sum of the both criterias:
=Count({<CRITERIA={'1) Dated - in time', '2) No date'}>} Identifier) / Count(Identifier)
The way you did it before, the last segment limit was smaller than the second one.
Juan Gerardo
See attached qvw. Is that what you mean?
Thank you!
This works perfectly
Thanks
Helen
Hello
Thanks for your help I have foudn it very useful and you too had the correct answer which has really helped me
Thanks
Helen