Hi All,

Could you please tell me how do I store my data into a qvd,

at the end of every quarter of the fiscal year.

And every time it stores, it should append to the earlier one and maintain a single qvd.

Thanks,

Bikash

1 Solution

Accepted Solutions
kaushiknsolanki
Partner Ambassador/MVP
Partner Ambassador/MVP

Hi,

    All you have to do is use incremental load.

    Below is an example of incremental load.

    If you have server then you can schedule this to run at the end of every quarter.

    For more information you can search community for Incremental load.

    Hope this will help you.

Regards,

Kaushik Solanki

Please remember to hit the 'Like' button and for helpful answers and resolutions, click on the 'Accept As Solution' button. Cheers!

View solution in original post

3 Replies
kaushiknsolanki
Partner Ambassador/MVP
Partner Ambassador/MVP

Hi,

    All you have to do is use incremental load.

    Below is an example of incremental load.

    If you have server then you can schedule this to run at the end of every quarter.

    For more information you can search community for Incremental load.

    Hope this will help you.

Regards,

Kaushik Solanki

Please remember to hit the 'Like' button and for helpful answers and resolutions, click on the 'Accept As Solution' button. Cheers!
Not applicable
Author

Hey Kaushik,

Thanks a lot.

Regards,

Bikash

rammuthiah
Creator III
Creator III

Can I get the script used in the above Data(2) qvw, as i am unable to load the file.