How to set a schedule to run 3 times a day on working days for an NPrinting version 16 report?

Hi all,

How do you set-up an NPrinting report to run 3 times a day at specified times?

E.g. I want the report to be delivered to the users at 08:00, 13:00, and a 17:00.

How to create a schedule like this?

1 Reply
Lech_Miszkiewicz
Partner Ambassador/MVP
Partner Ambassador/MVP

Hi John,

use this topic as a reference

NPrinting 17 - How to Generate Report every End Of Month

the additional info would be:

  • schedule your task to run every hour
  • schedule variable in Qlik which will return hour - smoething like: LET vReportHour = If(Hour(Now())=09 or Hour(Now()) =13 or Hour(Now()) = 17, 1,0)
  • use this variable in your condition in NPrinitng

cheers

LEch

I am not sure about formula "Hour()" but i will check it later on my PC and post again to confirm

cheers Lech, When applicable please mark the correct/appropriate replies as "solution" (you can mark up to 3 "solutions". Please LIKE threads if the provided solution is helpful to the problem.