Hi all,
We are currently upgrading our QlikView and NPrinting environments. QlikView from v11.2 to v12.4 and NPrinting v16.1 to v19. However, we are staggering our upgrade so we want to temporarily have QV v12.4 connected to our current NPrinting v16.1 setup.
Does anyone know if this will cause any issues with our existing reports?? From what I can tell from certain qlikcommunity threads is that this is possible, just not officially supported.
Please carefully review the information and video contained in the following links.
This information is also found in the article https://support.qlik.com/articles/000086526 that I provided earlier as well
The above is important information that applies to migrating:
or
In both cases you need to ensure you are running NP 16 SR 3 before attempting to migration. However, if you are using the individual report method, you may upgrade QlikView as indicated in the migration help page.
Kind regards...
Hello @qlik_Maestro
Please check the following articles to get informed about 'migrating' from NPrinting 16 to the NPrinting 19 platform.
QlikView 12.4 is not supported for use at this time with any version of NP 16 (as you already indicated). It is also advised that you do not upgrade QlikView prior to migrating to NP 19. This is also mentioned in the article above https://support.qlik.com/articles/000086526.
I trust that this is at least in part the guidance that you were looking for.
Kind regards...
Why is it recommended to not upgrade QV prior to NPrinting?? I am curious about how it can 'introduce unexpected problems and issues in the NPrinting Migration process'.
So would that mean that the conversion of our NPrinting reports will be easier if we have a QV 11.2 / NP 19 setup and the converted reports will run fine on an eventual QV 12.4 / NP 19 setup?
Please carefully review the information and video contained in the following links.
This information is also found in the article https://support.qlik.com/articles/000086526 that I provided earlier as well
The above is important information that applies to migrating:
or
In both cases you need to ensure you are running NP 16 SR 3 before attempting to migration. However, if you are using the individual report method, you may upgrade QlikView as indicated in the migration help page.
Kind regards...