Hello All,
I have tasks scheduled in QMC, in which tasks dependent on each other.
-Task1
-Task2
Every Day it was working without any issues (There shouldn't be any issues).
But today. Task1 reloaded completely but Task2 did not triggered at all.
Is there any logs or any logical reason which can describe that why task2 failed to trigger.
Hi,
Which is main task I mean task 1 or task2.
If reload schedule failed due to some sp reason you can check task log by clicking on task.
Moreover you can also view logs related to task in Qliktech folder.
thanks
Thanks for the suggestion deepika.
The main task is task1 which completely reloaded without any error or warnings, checked both Task log and document log. but Task2 did not trigered at all, therefore not log were created.
Try to run is manually and chk what will happen
Hi Alkesh,
Their is some issue with the sever i Guess try restarting the sever once
I agree, but that I can check only by tomorrow as I cannot start the reload now.
More over I think I need to answer the management as Y it failed. therefore need some logs of some logical answer that It failed and won't fail tomorrow.
R u using ODBC connection?
Hi
Which is the sever version your using
I would try by deleting task 2 and recreate it again and check if that helps.
Regards
ASHFAQ
Hello Ashfaq,
That is the solution you proposing, I want the reason for failure.
Thanks
Alkesh