Skip to main content
Announcements
See what Drew Clarke has to say about the Qlik Talend Cloud launch! READ THE BLOG
cancel
Showing results for 
Search instead for 
Did you mean: 
nagarajupinnibo
Creator
Creator

Run multiple tasks after completion of one task in qlikview

Hi,

I had 5 tasks namely task1,task2,task3,task4 and task 5.

First I will run task1 and after completion of task, remaining tasks need to start

I added task2,task3,task4,task5 as dependencies under task1.

But, Remaining tasks are not triggered after successful completion of task1..

Please provide solution and need some sample images how i can add multiple triggers for one task..

Thanks

Nagaraju

2 Replies
Not applicable

Hi,

You need set the other task to start on completion of the first task.

If I understand you correct, you like task 1 to run , then all other should run when task 1 is done?

So if task1 has run and is a success, the other tasks should start

tasktrigger.JPG.jpg

Not applicable

Sorry about posting wrong screen, you should use "On multiple events completed" it´s in the same configuration screen as posted.