I create a shedules in the script Qlikview.
How to deal holidays ? in the scipt ? in expressions
I want number of working day ?
Thanks
Best regards
try this
sarbatori_t:
LOAD * inline [sarbatori
1/1/2016
8/15/2016]
;
NoConcatenate
sarbatori:
load
concat(distinct CHR(39)&sarbatori&CHR(39),',') as concat_sarbatori
resident sarbatori_t;
drop table sarbatori_t;
let v_sarbatori=peek('concat_sarbatori',0,'sarbatori');
drop table sarbatori;
TempCalendar:
LOAD
date('1/1/2016' + rowno() - 1,'DD-MM-YYYY') AS DATA
AUTOGENERATE 1 While '1/1/2014' + rowno() - 1< yearend(today())-1;
NoConcatenate
pontaje_finale:
load
*,
NetWorkDays(DATA,DATA,$(v_sarbatori)) as workday;
load
*,
month(DATA) as luna,
year(DATA) as an,
'S'&ceil(Month(date(DATA,'MMM-YY') )/6) as Semestru,
Year(date(DATA,'MMM-YY') )&'-S'&ceil(Month(date(DATA,'MMM-YY') )/6) as An_Semestru,
'Q'&ceil(Month(date(DATA,'MMM-YY') )/3) as Trimestru,
dual(Year(date(DATA,'MMM-YY'))&'-Q'&ceil(Month(date(DATA,'MMM-YY'))/3),num(QuarterStart(date(DATA,'MMM-YY')))) as An_Trim,
date(makedate(year(DATA),month(DATA),'01'),'MMM-YYYY') as AnLuna,
floor(monthstart(date(makedate(year(DATA),month(DATA),'01'),'MMM-YY'))) as AnLuna_today,
'W'&week(date(DATA,'MMM-YY')) as Saptamana,
dual (year(DATA) &'-w'& week(date(DATA,'MMM-YY')) , num(weekstart(date(DATA,'MMM-YY')))) as AnSapt
resident TempCalendar;
drop table TempCalendar;
And please don't post multiple times the same request, this makes it hard to follow a discussion:
yes it's a mistake !
i 'll Watch the post.
Thanks for our reponses
try this
sarbatori_t:
LOAD * inline [sarbatori
1/1/2016
8/15/2016]
;
NoConcatenate
sarbatori:
load
concat(distinct CHR(39)&sarbatori&CHR(39),',') as concat_sarbatori
resident sarbatori_t;
drop table sarbatori_t;
let v_sarbatori=peek('concat_sarbatori',0,'sarbatori');
drop table sarbatori;
TempCalendar:
LOAD
date('1/1/2016' + rowno() - 1,'DD-MM-YYYY') AS DATA
AUTOGENERATE 1 While '1/1/2014' + rowno() - 1< yearend(today())-1;
NoConcatenate
pontaje_finale:
load
*,
NetWorkDays(DATA,DATA,$(v_sarbatori)) as workday;
load
*,
month(DATA) as luna,
year(DATA) as an,
'S'&ceil(Month(date(DATA,'MMM-YY') )/6) as Semestru,
Year(date(DATA,'MMM-YY') )&'-S'&ceil(Month(date(DATA,'MMM-YY') )/6) as An_Semestru,
'Q'&ceil(Month(date(DATA,'MMM-YY') )/3) as Trimestru,
dual(Year(date(DATA,'MMM-YY'))&'-Q'&ceil(Month(date(DATA,'MMM-YY'))/3),num(QuarterStart(date(DATA,'MMM-YY')))) as An_Trim,
date(makedate(year(DATA),month(DATA),'01'),'MMM-YYYY') as AnLuna,
floor(monthstart(date(makedate(year(DATA),month(DATA),'01'),'MMM-YY'))) as AnLuna_today,
'W'&week(date(DATA,'MMM-YY')) as Saptamana,
dual (year(DATA) &'-w'& week(date(DATA,'MMM-YY')) , num(weekstart(date(DATA,'MMM-YY')))) as AnSapt
resident TempCalendar;
drop table TempCalendar;
it works with your help florentina
Thanks you to all