Hello everybody,
I have a problem with a representation, in which I just can not get further.
Issue:
There are completed and open projects. These can be further subdivided into default (yes, no, new, etc.)
If projects are overdue, you can see how large the difference between plan and actual / calculated project end is.
How can you display this information on a combi-chart?
Completed and Open is to be seen as a separate bar, the subcategories should be stacked, the warp as a point above the bar, so that one may see the monthly progression,
Oh yes:
- how to make it possible that project is marked only as "new" when the month, or the year was selected, where they were added. In later months / years, they are no longer new ...
Does somebody have any idea?
Best regards,
Michael
Hi Michael,
maybe you can just mark the field: properties -> presentation -> plot values inside segments
Tim
Dear Tim,
Not exactly what I had in mind, but I will use it. It's a smart solution.
Regard,
Michael