I am trying to build an MRP view in Qlikview and I just about have everything working with one exception, getting the Planned Order Release to show up in the right place.
I am calculating that for a given month I need to place an order or I will fall short of needs. That particular item has a 120 day lead time, so the Planned Order Release needs to be 4 months prior to the Planned Order Receipt field.
Does anyone have any idea how to do this? I am attaching what I am working on.
The filed that I am struggling with is Planned Order Releases, which should be the same number as the Planned Order Receipts field, just 120 days earlier.
Thanks,
Mike
Maybe like attached?
Maybe like attached?
Thank you very much, I believe I can make that work.