Qlik Community

Ask a Question

QlikView App Dev

Discussion Board for collaboration related to QlikView App Development.

Announcements
Our next Qlik Insider session will cover new key capabilities. Join us August 11th REGISTER TODAY
cancel
Showing results for 
Search instead for 
Did you mean: 
vireshkolagimat
Creator III
Creator III

Disable tasks in QMC

Hi All,

I have 5 tasks which are depending on each other. In order to stop the tasks execution, is it ok if i disable only the first task? OR Do i need to disable all tasks manually. By the way all the tasks are depending on each other.

Like:

Task1

     Task2

            Task3

                    Task4

Here the task2 will execute only on the  successful execution of Task1. Similarly for other tasks have dependency.

Thank you.

Regards,

Viresh

1 Solution

Accepted Solutions
rahulpawarb
Specialist III
Specialist III

You can disable the first task; this will do the trick; if someone triggers the intermediate task then subsequent tasks will be started. So disabling all the tasks will help you to avoid unnecessary execution of other tasks.

Hope this will help,

Regards!

Rahul Pawar

View solution in original post

2 Replies
Muthu
Partner
Partner

Disabling only task1 would be fine.

rahulpawarb
Specialist III
Specialist III

You can disable the first task; this will do the trick; if someone triggers the intermediate task then subsequent tasks will be started. So disabling all the tasks will help you to avoid unnecessary execution of other tasks.

Hope this will help,

Regards!

Rahul Pawar

View solution in original post