Hello,
I have a gantt chart, where the dates are starting from 1900. I am showing the chart based on the duration. The duration is calculated based on project end date - project start date. The chart and its properties are shown in the attach images. Can someone please suggest how can I make the chart axis to start from 2011 rather than 1900
Thanks
Arif
hei
uncheck the forced 0 check box
When i try to uncheck force 0, the dates become correct, but then the data totally disappears.
i think you need to use bar offset in the expression, off setting the bar by start date