Gantt chart not behaving like I expect

Gantt chart looks like this: http://i46.tinypic.com/nlo08p.gif

Dimension: ProjectName

Expression Design Phase: Max (ConstructionStart) - Min (Design Start)

Expression Construction Phase: Max (ConstructionEnd) - Min (ConstructionStart)

My data looks like this: http://i45.tinypic.com/2cgcydu.gif

So what's going on?  Design and construction should be staggered.  But they're not...?

1 Solution

Accepted Solutions
nagaiank
Specialist III
Specialist III

For the second expression, click on + and enter the first expression as Bar Offset if you want to see the bars one below the other.

Message was edited by: Nagaian Krishnamoorthy

View solution in original post

4 Replies
swuehl
MVP
MVP

Have you select the Stacked style in style tab of the chart properties?

Could you upload a small sample file or your input data here?

nagaiank
Specialist III
Specialist III

For the second expression, click on + and enter the first expression as Bar Offset if you want to see the bars one below the other.

Message was edited by: Nagaian Krishnamoorthy

Not applicable
Author

Stacked style causes it to look like this: http://i47.tinypic.com/205qg3l.gif

I've attached the Excel sheet I was working on.  Or here: http://dl.dropbox.com/u/46307240/Gantt_sample.xlsx

Not applicable
Author

Ahh, that did the trick.  I needed to offset 'Construction' by its start date.  Thanks!  You helped me again.