Hi Guys,
I'm currently stuck in the middle to change from week number in X axis to Date.
Please advise me.
In this discussion I'm attached together with my source file and below my script.
Directory;
LOAD @1,
@2,
@3,
@4,
@5,
@6,
@7,
@8,
@9,
@10,
@11,
@12,
@13,
@14,
@15,
@16,
@17,
@18,
@19,
@20,
@21,
@22,
@23,
@24,
@25,
@26,
@27,
@28,
@29,
@30,
@31,
@32,
@33,
@34,
@35,
@36,
@37,
@38,
@39,
@40,
@41,
@42,
@43,
@44,
@45,
@46,
@47,
@48,
@49,
@50,
@51,
@52,
@53,
@54,
@55,
@56
FROM
[..\..\..\QlikViewSupplyDemandSharedFolder\Weekly\MatchedPlan\MatchedPlan2011.xlsx]
(ooxml, no labels, header is 3 lines, table is Vegetable, filters(
Replace(1, top, StrCnd(null)),
Replace(2, top, StrCnd(null)),
Top(1, 'Item_code'),
Remove(Row, RowCnd(CellValue, 1, StrCnd(null))),
Remove(Row, RowCnd(CellValue, 1, StrCnd(contain, 'SKU'))),
Top(2, 'Budget'),
Top(2, 'Budgets'),
Remove(Row, RowCnd(Compound,
RowCnd(CellValue, 2, StrCnd(contain, 'Matched', not)),
RowCnd(CellValue, 2, StrCnd(contain, 'Budgets', not))
)),
Top(3, 'Remarks'),
Remove(Row, RowCnd(CellValue, 3, StrCnd(null))),
Remove(Row, RowCnd(Compound,
RowCnd(CellValue, 3, StrCnd(contain, 'Remarks', not)),
RowCnd(CellValue, 3, StrCnd(contain, 'Supply Demand', not))
))
))
Where (@1)='Item_code';
Hi Guy,
this is example with current year ('2011') and Mondays:
LOAD
....
MakeWeekDate( '2011' , num(Mid(@4,6 ),'00')) AS @4,
MakeWeekDate( '2011' , num(Mid(@5,6 ),'00')) AS @5,
. . .
HtH
Roland
Hi Roland,
If I used the statement it will shown the 1st day of the week which is Monday date only.
How should I do if the column auto create for 1 week by 7 days and the value also will be devide to 7 column base on th days meaning start from Monday to Sunday.
Requisitioner aid
Hairul