Skip to main content
Announcements
See what Drew Clarke has to say about the Qlik Talend Cloud launch! READ THE BLOG
cancel
Showing results for 
Search instead for 
Did you mean: 
Anonymous
Not applicable

INCREMENTAL RECHARGE

good afternoon

I need to know how to do an incremental load if I do not have a date field

recharge can be generated without this field?

I hope you can help

regards

Luis Espinoza

1 Reply
maxgro
MVP
MVP

you need a field to identify the record to load after your previous load;

the  field could be a date, a counter or anything that allows you to understand the changed or inserted records ((I exclude the case with deletion you can find in the link below) in the source database but not yet in Qlik qvd

https://help.qlik.com/en-US/qlikview/12.0/Subsystems/Client/Content/QVD_Incremental.htm