Reschedule reload task

Hello, everyone

Is there a way i can reschedule a reload task based in a condition?

I have a query that works fine everyday, but every first day of the month the database takes an unkown amount of time processing the data. So i made a query where i check if the proccessment is over, and i wanna know if there is some way i can do this query at reload scheduled time and is procces is not over try again 1 hour later.

Thanks in advance,

Julio.

1 Solution

Accepted Solutions
Peter_Cammaert
Partner - Champion III
Partner - Champion III

Maybe by letting the database engine trigger the task when it is done preparing the data? This is way more efficient than either polling a dataase before attempting a reload, or by trying to start a reload over and over again until it finally succeeds.

View solution in original post

2 Replies
Peter_Cammaert
Partner - Champion III
Partner - Champion III

Maybe by letting the database engine trigger the task when it is done preparing the data? This is way more efficient than either polling a dataase before attempting a reload, or by trying to start a reload over and over again until it finally succeeds.

Not applicable
Author

Thanks!

I found this topic in the community talking about EDX.

Using EDX in QlikView 11

Im gonna check it.