Hi guys,
Need some help on priority please.
I have two tables that are getting incrementally loaded from SAP . I have an application that has two grids (Table boxes) pertaining to each table.I have defined a macro on a button to push the data into Oracle .My requirement was for this activity to happen on an hourly basis.So I have scheduled it in QV Management console.But it isnt happening correctly.If I explicitly Push the button the macro gets called and the data correctly gets loaded into the respective tables in Oracle.However this is not happening via the scheduler.
I have no idea as to why that is failing.Someone pls guide me through the steps to properly schedule i)The Generator (that generates incremental data every hour) ii) The application which contains the two grids of the respective tables (objects ie data sources for the macro) ii) MOST IMPORTANT - The macro which will push the data into the tables.
Thanks alot
Rochelle