Urgent - Help required to create a Progress Chart

Hello Team,

I have the following columns already loaded in qvw. I want to create a Progress chart (over the time period) to show the progress.

Table:

ProjectName   RequirementExpectedDate    RequirementActualDate    ProjectGoLiveDate

xxx                         1/1/2016                              1/15/2016                              2/15/2016

yyy                         2/10/2015                             2/10/2015                             2/1/2015

zzz                         11/11/2015                           11/12/2015                           11/20/2015


Now my requirement is to show how the difference of RequirementExpectedDate and RequirementActualDate has progressed over the period (ProjectGoLiveDate).


X-Axis should show the date difference (in numbers) in Percentage.

Y -Axis should show the GoLiveMonths



Can you all please guide me.




Thanks

5 Replies
Peter_Cammaert
Partner - Champion III
Partner - Champion III

Maybe you should first fix your dates. Project xxx has a ProjectGoLiveDate of 2/15/2016 and project zzz has a PrjectGoLiveDate of 29/11/2015. You can't have it both ways (you can, but it's better to fix what is wrong)

Peter

sayadutt
Creator
Creator
Author

Hi Peter,

That was a typo. I have fixed it. Can you guide here.

Thanks in advance!!!

Peter_Cammaert
Partner - Champion III
Partner - Champion III

Based on your minimal details, this is what I came up with. Is this what you want?

Progress Chart thread206226.jpg

Best,

Peter

sayadutt
Creator
Creator
Author

Can we have x-axis in Percentage please.

The differnce should be Actual minus Expected, so always positive or zero. (not negative)

Also, can we apply NetWorkDays function.. instead of avg, so that we get only the working dayscount excluding weekends.

Thanks

PradeepReddy
Specialist II
Specialist II

can you elaborate your requirement..

X-Axis  (numbers in %) --> what % you want to showcase?