Hi All
I have few fields in the list box like subsystem,project,days, weekdays are fields based section of values in the fields the graph should display .
But will i am selecting the values
shows 252/252 (100%). Instead it should show the total of all the days it spent in all subsystems 252/488 (51.71%) ( where 488 is total if we didn’t select the subsystem).
can any one help me on this irrespective of the selection it should display total of the all days .
Ok. Give a try with the below and see:
You said:
( where 488 is total if we didn’t select the subsystem).
=num(SUM({<ir.status={'In Progress'}, ir.rma_days_open={">=$(days)"}>} metric.total_time)/SUM({ <ir.status={'In Progress'}, subsystem=,ir.rma_days_open={">=$(days)"}>} total<ir.project> metric.total_time),'#.00%')
&chr(13)&
'('&num(SUM({<ir.status={'In Progress'}, ir.rma_days_open={">=$(days)"}>} metric.total_time),'0')&'/'&num(SUM({<ir.status={'In Progress'}, subsystem=,ir.rma_days_open={">=$(days)"}>} total<ir.project> metric.total_time),'0')&')'
Note: I removed 1 and included subsystem. If the field name is not subsystem then please modify accordingly.
May be as below:
=num(SUM({<ir.status={'In Progress'}, ir.rma_days_open={">=$(days)"}>} metric.total_time)/SUM({ 1 <ir.status={'In Progress'}, ir.rma_days_open={">=$(days)"}>} total<ir.project> metric.total_time),'#.00%')
&chr(13)&
'('&num(SUM({<ir.status={'In Progress'}, ir.rma_days_open={">=$(days)"}>} metric.total_time),'0')&'/'&num(SUM({ 1 <ir.status={'In Progress'}, ir.rma_days_open={">=$(days)"}>} total<ir.project> metric.total_time),'0')&')'
Note: Added 1 in the expression with color coded.
Hi Thirmula
Thanks for the fast response . if i passed the as you said it is calculating all the project and days . but my selection is only for particular project and days spent to that particular project
If you can,please share a sample app and the expected output....
i Cant share the app the data around 1 Gb
Ok. Give a try with the below and see:
You said:
( where 488 is total if we didn’t select the subsystem).
=num(SUM({<ir.status={'In Progress'}, ir.rma_days_open={">=$(days)"}>} metric.total_time)/SUM({ <ir.status={'In Progress'}, subsystem=,ir.rma_days_open={">=$(days)"}>} total<ir.project> metric.total_time),'#.00%')
&chr(13)&
'('&num(SUM({<ir.status={'In Progress'}, ir.rma_days_open={">=$(days)"}>} metric.total_time),'0')&'/'&num(SUM({<ir.status={'In Progress'}, subsystem=,ir.rma_days_open={">=$(days)"}>} total<ir.project> metric.total_time),'0')&')'
Note: I removed 1 and included subsystem. If the field name is not subsystem then please modify accordingly.
This is much easier to analyse if you remove the decoration:
SUM({<ir.status={'In Progress'}, ir.rma_days_open={">=$(days)"}>}
metric.total_time)
/
SUM({<ir.status={'In Progress'}, ir.rma_days_open={">=$(days)"}>}
total <ir.project> metric.total_time)
The expression looks correct, but I expect your problem is the partial total. If ir.project is a dimension, then you will always get 100%, so either remove ir.project from the partial total (make into a normal full total, or partial by some other field(s)), or take ir.project out of the dimensions.
Once you have got the expression working, then you can reapply the decoration.
Thanks so much Thirumala ,it worked perfectly
You are welcome and I am glad to hear that it worked....