HI
Can someone please help me with below requirement Logic and function to be used.
I need to filter by JOB and Task with start and end time for JO and event respectively.
Log Table:
date | time | Event |
15-07-2019 | 1.00 Am | Job Start:Turning |
15-07-2019 | 2.00 Am | Task Start: Turning Componrnt 1 load tool |
15-07-2019 | 2.30 Am | tool loaded |
15-07-2019 | 2.40 Am | Machining |
15-07-2019 | 3.00 Am | Task End: Turning Componrnt 1 load tool |
15-07-2019 | 3.30 Am | Task Start: Turning Componrnt 2 load tool |
15-07-2019 | 4.00 Am | tool loaded |
15-07-2019 | 5.00 Am | Machining |
15-07-2019 | 5.15 Am | Task End:Turning Componrnt 2 load tool |
15-07-2019 | 5.55 Am | Job End: Turning |
15-07-2019 | 6.12 Am | Job Start:Milling |
15-07-2019 | 6.30 Am | Task Start: Milling Componrnt 1 load tool |
15-07-2019 | 7.00 Am | tool loaded |
15-07-2019 | 7.20 Am | Machining |
15-07-2019 | 7.25 Am | Task End:Milling Componrnt 1 load tool |
15-07-2019 | 7.40 Am | Task Start: Milling Componrnt 2 load tool |
15-07-2019 | 7.50 Am | tool loaded |
15-07-2019 | 8.05 Am | Machining |
15-07-2019 | 8.15 Am | Task End: Milling Componrnt 2 load tool |
15-07-2019 | 8.18 Am | Job End: Milling |
15-07-2019 | 8.30 Am | Job Start :Cleaning |
15-07-2019 | 8.35 AM | Task Start: CleaningComponrnt 2 load tool |
15-07-2019 | 8.40 Am | tool loaded |
15-07-2019 | 8.45 Am | Cleaning |
15-07-2019 | 8.45 Am | Task End: CleaningComponrnt 2 load tool |
15-07-2019 | 8.45 Am | Job End:Cleaning |
I need to get table similar so that i can filter in the front end by Job and Task
date | time | Event | JOB | Start Time | End Time |
15-07-2019 | 1.00 Am | Job Start:Turning | Turning | 1.00 Am | 5.55 Am |
15-07-2019 | 2.00 Am | Task Start: Turning Componrnt 1 load tool | Turning | 1.00 Am | 5.55 Am |
15-07-2019 | 2.30 Am | tool loaded | Turning | 1.00 Am | 5.55 Am |
15-07-2019 | 2.40 Am | Machining | Turning | 1.00 Am | 5.55 Am |
15-07-2019 | 3.00 Am | Task End: Turning Componrnt 1 load tool | Turning | 1.00 Am | 5.55 Am |
15-07-2019 | 3.30 Am | Task Start: Turning Componrnt 2 load tool | Turning | 1.00 Am | 5.55 Am |
15-07-2019 | 4.00 Am | tool loaded | Turning | 1.00 Am | 5.55 Am |
15-07-2019 | 5.00 Am | Machining | Turning | 1.00 Am | 5.55 Am |
15-07-2019 | 5.15 Am | Task End:Turning Componrnt 2 load tool | Turning | 1.00 Am | 5.55 Am |
15-07-2019 | 5.55 Am | Job End: Turning | Turning | 1.00 Am | 5.55 Am |
15-07-2019 | 6.12 Am | Job Start:Milling | Milling | 6.12 Am | 8.18 Am |
15-07-2019 | 6.30 Am | Task Start: Milling Componrnt 1 load tool | Milling | 6.12 Am | 8.18 Am |
15-07-2019 | 7.00 Am | tool loaded | Milling | 6.12 Am | 8.18 Am |
15-07-2019 | 7.20 Am | Machining | Milling | 6.12 Am | 8.18 Am |
15-07-2019 | 7.25 Am | Task End:Milling Componrnt 1 load tool | Milling | 6.12 Am | 8.18 Am |
15-07-2019 | 7.40 Am | Task Start: Milling Componrnt 2 load tool | Milling | 6.12 Am | 8.18 Am |
15-07-2019 | 7.50 Am | tool loaded | Milling | 6.12 Am | 8.18 Am |
15-07-2019 | 8.05 Am | Machining | Milling | 6.12 Am | 8.18 Am |
15-07-2019 | 8.15 Am | Task End: Milling Component 2 load tool | Milling | 6.12 Am | 8.18 Am |
15-07-2019 | 8.18 Am | Job End: Milling | Milling | 6.12 Am | 8.18 Am |
15-07-2019 | 8.30 Am | Job Start :Cleaning | Cleaning | 8.30 Am | 8.45 Am |
15-07-2019 | 8.35 AM | Task Start: CleaningComponrnt 2 load tool | Cleaning | 8.30 Am | 8.45 Am |
15-07-2019 | 8.40 Am | tool loaded | Cleaning | 8.30 Am | 8.45 Am |
15-07-2019 | 8.45 Am | Cleaning | Cleaning | 8.30 Am | 8.45 Am |
15-07-2019 | 8.45 Am | Task End: CleaningComponrnt 2 load tool | Cleaning | 8.30 Am | 8.45 Am |
15-07-2019 | 8.45 Am | Job End:Cleaning | Cleaning | 8.30 Am | 8.45 Am |
[ NOTE: to show any contributor that you like and appreciate their answers please CLICK the like icon (thumbs up) ]
Here's a way to do it:
[ NOTE: to show any contributor that you like and appreciate their answers please CLICK the like icon (thumbs up) ]
Here's a way to do it:
Thanks a lot Petter, Worked well