Hello Community!
I am working with a 'EndDate' value and have to calculate the 'StartDate' value based on a duration of 17. The easy answer is . . .
AddDays(EndDate, -10) as StartDate
However, when calculating the StartDate, I need to subtract 17 work days and exclude weekends from my calculation.
In simple mathematical terms, I want to solve for EndDate - 17 working days = StartDate
Without both a start and finish date, I can not use the NetworkDays function. (I've reviewed this post: Excluding weekends from one date minus another..; different issue.)
Any suggestions or examples? Either would be greatly appreciated.
Regards,
Ellen