Depending Reload not trigger.

Hi All,

currantly i am facing one issue in QV server 11.2 sr3, reload scheduling and trigger is not working on dependant task.

if parent task completed sucessfully still the child or dependent task not starting.

please help.

Rehgards

Rajendra

Labels (1)
1 Solution

Accepted Solutions
Not applicable
Author

Hi All,

Thanks for replying, I have solve the problem by replacing QVPR with backup.

Regards,

Rajendra

View solution in original post

8 Replies
luis_pimentel
Partner - Creator III
Partner - Creator III

could you share a screenshot of your qvw schedule reload time?

magavi_framsteg
Partner - Creator III
Partner - Creator III

Hi Rajendra.

Tasks will *only* reload if they have at least one trigger.

The dependencies are optional, and they work like this:

- Task is triggered to run

- Dependencies are evaluated to see if they are met or not

- Run task or don't run task depending on result of previous dependencies check

//Regards

Magnus Åvitsland

Framsteg.com

giakoum
Partner - Master II
Partner - Master II

completed successfully without any warnings? is there a yellow triangle?

Not applicable
Author

reload schedule.png

Not applicable
Author

I have created dependate task on sucessfull event... please look the above screen shot

giakoum
Partner - Master II
Partner - Master II

looks ok. why is it newer? Even for the 1st one?

Bill_Britt
Former Employee
Former Employee


Hi,

Are you running Cluster Distribution services?

Bill

Bill - Principal Technical Support Engineer at Qlik
To help users find verified answers, please don't forget to use the "Accept as Solution" button on any posts that helped you resolve your problem or question.
Not applicable
Author

Hi All,

Thanks for replying, I have solve the problem by replacing QVPR with backup.

Regards,

Rajendra