Hello

I have a qvw that is scheduled to run every hour. If I want to disable my schedule without disabling my task what would be the best way to do it on the Console?

Thanks

Riz

1 Solution

Accepted Solutions
Highlighted
MVP
MVP

Re: Disable my schedule

disable the trigger (if you have publisher)

or set the schedule to none (if you don't have)

View solution in original post

4 Replies
Highlighted
Esteemed Contributor

Re: Disable my schedule

Hi,

what exactly do you mean by "without disabling my task"?

If you disable the reload_task in QMC (there is a checkbox "None"), the app can still be reloaded locally or even manually in the console. Is that what you mean?

HTH

Best regards,

DataNibbler

Highlighted
MVP
MVP

Re: Disable my schedule

disable the trigger (if you have publisher)

or set the schedule to none (if you don't have)

View solution in original post

Highlighted
Not applicable

Re: Disable my schedule

Hello

We do have Publisher.

So I have a qvw that runs every hour. How do I disable its schedule so that it does not refresh automatically and I can refresh whenever I want to.

Please list out the steps

Thanks

Highlighted

Re: Disable my schedule

Hello Rizwan,

go to QEMC --> Status --> task --> select any task that you need to disable --> click on edit as highlighted and image and uncheck unable.

Hope it helps