Qlik Community

QlikView Deployment

Discussion Board for collaboration related to QlikView Deployment.

Not applicable

Qlikview Server - Creating an ad-hoc reload

Hi All,

Is it possible to create a ad-hoc reload on the Qlikview Server without a scheduled run time?

Similarly, is it possible to schedule a task through the Qlikview Server but disable the ad-hoc reload functionality?

Thanks.

1 Solution

Accepted Solutions
Employee
Employee

Qlikview Server - Creating an ad-hoc reload

1. Yes, it is called EDX in Qlikview. See the Qlikview Server reference manual for 8.50 or 9 (the differ in functionality on EDX) for code examples.

2. I'm not sure what you mean here.. ?

3 Replies
Employee
Employee

Qlikview Server - Creating an ad-hoc reload

1. Yes, it is called EDX in Qlikview. See the Qlikview Server reference manual for 8.50 or 9 (the differ in functionality on EDX) for code examples.

2. I'm not sure what you mean here.. ?

Not applicable

Qlikview Server - Creating an ad-hoc reload

Thanks Stefan,

I meant is it possible to set up a scheduled task so it is viewed in the Status tab of the QMC, but users cannot manually start/stop the task.

Employee
Employee

Qlikview Server - Creating an ad-hoc reload

That I am actually unsure about. What version?

Community Browser