Reload Schedule set to Weekly-Monday-7:00 am but it runs every day

So this looks like a straight up bug to me.

I have documents on a Reload Schedule set to Weekly-Monday-7:00 am but those docs reload every day

I thought maybe it was just in a weird state, but it doesn't matter if I disable or reconfigure it and change it back.

Is this a known bug with QlikView 9 Server?

Is their a patch?

Can anybody else duplicate this issue?

1 Solution

Accepted Solutions
johnw
Champion III
Champion III


Jared Barneck wrote: Again, I found my own answer. Is anyone actually monitoring this forum?


As a possible workaround, I'd try running it as a daily job, with "Run only on:" and "Monday" both checked. Maybe that would work where the weekly approach doesn't.

View solution in original post

3 Replies
Not applicable
Author

Again, I found my own answer. Is anyone actually monitoring this forum?

http://community.qlik.com/forums/p/22179/85210.aspx
It is a bug id 24318, which is planned to be fixed in the next release (9.0 SR3) coming in February/2010.

johnw
Champion III
Champion III


Jared Barneck wrote: Again, I found my own answer. Is anyone actually monitoring this forum?


As a possible workaround, I'd try running it as a daily job, with "Run only on:" and "Monday" both checked. Maybe that would work where the weekly approach doesn't.

Not applicable
Author

Thanks, that is what I am doing now and it works.