Reload jobs are not running in QMC ( Qvw Reload Schedule failed )

Hi Frnz,

I scheduled at 5AM everyday in QlikView Server. 1 Tier only gave error like: Failed to create qlikview engine.

If i schedule after 5 mins, it is reloaded successfully, but if i schedule for tomorrow, it is giving failure.

I have attached log file and Server log status.

Please help me.

6 Replies
manucamon
Valued Contributor III

Re: Reload jobs are not running in QMC ( Qvw Reload Schedule failed )

Hi tulasiram,

You have two errors there:

     1.- Your ODBC cannot connect, it seems that there are an communication error, or an resources error.

     2.- Engine error is because there aren't free resources on server to manage this job.

Change your execution hour to early or late, because you haven't some resources at this time.

Regards!!

Highlighted
tulasiram_bitra
New Contributor III

Re: Reload jobs are not running in QMC ( Qvw Reload Schedule failed )

Hi Frnz,

We have installed sql server data tools SSIS, SQL Server Mangament Studio and QlikView in same machine ( UAT Server ).

Is there any problem ? I think i am getting problem in reloading because of this.

Is it true ? Please let me know Guys ..

manucamon
Valued Contributor III

Re: Reload jobs are not running in QMC ( Qvw Reload Schedule failed )

Hi tulasiram,

How many memmory has assigned SQL Server?

Regards!

tulasiram_bitra
New Contributor III

Re: Reload jobs are not running in QMC ( Qvw Reload Schedule failed )

by using this expression: SELECT physical_memory_kb FROM sys.dm_os_sys_info;

I got 67108404 Kb ( 67 GB ).

My server RAM : 64 Gb

Qlikview Application size: 40 MB

manucamon
Valued Contributor III

Re: Reload jobs are not running in QMC ( Qvw Reload Schedule failed )

So what I can see, you have assigned all system memory to the database server, I think it would be better to limit it and leave at least 10GB for the rest of the system.


Regards!

nizamsha
Valued Contributor II

Re: Reload jobs are not running in QMC ( Qvw Reload Schedule failed )

I think U have some ODBC issue kindly check these are problem i hope

check ur database schedule is going on when u try to trigger through server if its reload is going on chances are there to get the status Failed

and also check weather the  same data base  is used in another application at the same time when u triggered the application on server then also u have a chance ur reload will get failed after

EG: consider you have sales app and another developer  is also using  the same sales app and if u both are reloading the app at the same time hitting the database some once applciation will get failed and another person application will take some minutes extra than a usual reload time