Trigger a task on multiple events

Hi Experts,

I need to trigger a task on completion of multiple other tasks. I have tried the trigger "On multiple events completed", but somehow it doesn't work. The dependent task never starts.

Untitled.png

Can anyone please help me to find what's going wrong here?

Thanks,

Bhalchandra

10 Replies
alexandros17
Partner - Champion III
Partner - Champion III

But other tasks that you called Job1 and Job2 have been scheduled?

Not applicable
Author

Yes. They are scheduled to trigger on same common event.

alexandros17
Partner - Champion III
Partner - Champion III

So they are scheduled depending on other tasks?

Not applicable
Author

Yes.

jerrysvensson
Partner - Specialist II
Partner - Specialist II

Which version of QV are you running?

Not applicable
Author

Version 11

alexandros17
Partner - Champion III
Partner - Champion III

Ok But these other task are scheduled that is

MAIN TASK depends on Job1, Job2 Both scheduled

Job1 depends on Job11 (Scheduled)?

Job2 depends on Job22 (Scheduled)?

I think that at the end of this chain something doesn't work

jerrysvensson
Partner - Specialist II
Partner - Specialist II

Which SR?

Like 11 sr2 or 11.2 Sr1?

There was a problem with multiple events in one SR release on 11.2

Not applicable
Author

Hi Alessandro,

The chain is something like this:

MAIN TASK depends on Job1, Job2 Both scheduled

Job1 depends on Job11 On EDX

Job2 depends on Job22 On EDX

Hi Jerry,

Its 11 SR2