how to know what projects will finish in two week

Hello Everybody

i have been having a problem figuring out how to know what projects will finish  in two week  as my fields are as follow

StartingDate

ActualStartingDate

FinishingDate

ActualFinishingDate

PRO_ID

PRO_Name

Project_Precent_Compeleted

Many Thanks

1 Reply
mwoolf
Honored Contributor II

Re: how to know what projects will finish in two week

Maybe something like:

if((ActualFinishingDate-ActualStartingDate)<=13,1,0) as TwoWeekFlag