How to schedule a task in QMC to run twice a day at 10:00 AM once and 4:00 PM once???

Hi,

I'm new to qlikview and now i'm stuck with below problem. Kindly help me with the solution for it.

Problem:

On a daily basis I have to run a task in QMC twice a day i.e. at 10:00 AM once and 4:00 PM Once.

I have tried below:

I tried with run only option but with this option it running with the specified interval  considering run between timings. 
I will be achieving desired output for only current day for next day again it is taking some other interval (tried with enabling max number of executions to 2 and even by disabling it). 

Any help is appriciated 

Thanks in Advance

Labels (1)
1 Reply
kaushiknsolanki
Partner Ambassador/MVP
Partner Ambassador/MVP

Hi,

My suggestion will be you create two task. One to run at 10 AM and another to run at 4 PM.

Advantage of this is you can monitor each of this task individually.

 

Regards,

Kaushik Solanki