Hi,

I have recently upgraded from QlikView 9 SR4 to 10 SR2. When changing around some of the documents in the scheduler I noticed that documents I have deleted still remain in the list for reloading on a nightly basis.  I cannot seem to find a way of removing them.  Can anyone help?

Thanks,

Paul

1 Solution

Accepted Solutions
Partner
Partner

QlikView keeps documents in scheduler

Hi Paul,

I've also had this problem a while ago. You basically have to:

1. create a dummy qvw file (with the same name as the task's file) in the folder

2. disable the task

3. delete the dummy file you've created.

Voilá.

Hope this helps.

Regards,

Fernando

2 Replies
Partner
Partner

QlikView keeps documents in scheduler

Hi Paul,

I've also had this problem a while ago. You basically have to:

1. create a dummy qvw file (with the same name as the task's file) in the folder

2. disable the task

3. delete the dummy file you've created.

Voilá.

Hope this helps.

Regards,