Dear all,
I need to create a task that only run once a day (eg 11pm) but it should only run after the 2 other tasks are completed. The 2 other tasks run multiple times a day. Any idea how can I set up the trigger based on this scenario?
Hi Khim,
Add "On multiple events completed" trigger on the task you want to trigger based on 2 other tasks (select "Task Finished Trigger").
So what I think you can do is setup a task trigger to run daily at the time needed. Also in the trigger tab there is a task dependencies section, here I would add the 2 other tasks you want as dependencies to have run successfully.