QMC Task Trigger - help needed

Hi, Please help me creating a task that should be triggered to run:

1. Every hour between 11 PM ET till 8 AM ET.

and

2. Run on Day 1 till Day 10 of each month excluding Saturday and Sunday

I created a task with two triggers like below but it is not working as expected. The task is running on Day 11, Day 12 until last day of the month instead of just being stopped on Day 11. Thanks in advance for any suggestions.

qmcmultitrigger1.png

qmcmultitrigger2.png

qmcmultitrigger3.png

2 Replies
bbi_mba_76
Partner - Specialist
Partner - Specialist

Hi,

you have two separate trigger, so the first will run every day, the second at 11:00 only in the selected day (1-11 of each month).

You have to create only one trigger to do what you want, if I understand well.

sudeepkm
Specialist III
Specialist III
Author

Hi Thanks for the quick response.

Can you please advice me a way of creating one trigger that can satisfy the below schedule

1. Every hour between 11 PM ET till 8 AM ET.

and

2. Run on Day 1 till Day 10 of each month excluding Saturday and Sunday