Task Dependancies on QMC

Hi,

Wondering if anyone on the community could assist me with this issue.

Please view image below:

QV Job Dependancies.png

As you can see I have two TP jobs dependant on their respective QSS load jobs.

My intention is to have the QSS load jobs to run on Mondays and Tuesdays and then run the TP jobs to run on Wednesday, excluding the QSS jobs, as this will shave off some considerable amount of time during refresh. What would you recommended is the best course of action?

1 Reply
Peter_Cammaert
Partner - Champion III
Partner - Champion III

When do you want to refresh the end-user "Aggr" documents? Every day, even if both source documents are never up to date at the same time? Or only after the TPP documents get updated as well?

If completion time is a constraint, then why don't you run the QSS and TP jobs in parallel?